On Thanksgiving morning, the 13 basins stepping down the middle of Meridian Hill Park are empty. Neighbors who have walked past since 2019 saw the same dry concrete for seven years. This year the dry basins mean the fountain is off for the season, which is a different situation. Last week the National Park Service said that it begins winterizing the fountains at Meridian Hill Park, Chevy Chase Circle, Georgetown Waterfront Park and the Kahlil Gibran Memorial as colder weather arrives in mid-November, and that they "will remain off until spring 2027," as PoPville reported on November 18.
The park on 16th Street, which many neighbors in Columbia Heights and Adams Morgan call Malcolm X Park, starts the winter with a working fountain on a normal seasonal pause, lawns with no fences around them, and a known date when the water should return. None of those was true a year ago.
The cascade had trouble long before it went fully dry. E&E News reported in July that it was shut down for weeks in 2016 when a pump motor broke and again in 2018 for pipe breaks and leaks. The Park Service turned it off in 2019 when work on the lower plaza began. According to the NPS page for the park, crews working on the plaza found that several critical fountain components needed replacing and that damaged concrete needed extensive repair.
The lower plaza project ran from December 2020 through February 2023. It added an accessible route from the corner of 16th Street and Florida Avenue/W Street up to the lower plaza and across to the plaza in front of the James Buchanan Memorial. The fountain stayed dry after that work ended.
The 2026 rehabilitation brought it back. The Park Service lists the work as cleaning and restoring historic concrete and masonry, new plantings, turf restoration, tree pruning, irrigation inspection, storm-drain cleaning, bench restoration and lighting repairs, plus repairs to the cascade and the park's other fountains. Terra Constructs says it was the Park Service's prime contractor for the rehabilitation, including the cascade and its connected fountain systems, on a five-month schedule. E&E put the cost of the cascade renovation at $10.7 million, within a Park Service effort of nearly $60 million to rehabilitate fountains around the city. City Cast DC described the wider park renovation as a $16 million project.
The lower plaza, cascade and reflecting pool reopened on May 14, 2026. City Cast DC was there the weekend after and wrote that toddlers splashed in the reflecting pool and sunbathers listened to the water fall through the 13 basins. Lindsey Appiah, the District's deputy mayor for public safety, told City Cast the park was so crowded it felt like people were making "pilgrimages" to see it.
A fountain that had been dry for seven years needed adjusting once it was running again. NPS said in May that it would keep testing water levels and flow rate after the reopening. In early July the water turned brown. According to E&E News, the Interior Department traced the color to sediment released from two water lines that had long been out of service. The Park Service said it was continuing "to fine tune the fountain's operations" and expected the water to run clean again within 24 to 36 hours.
The winter shutoff that started this month is the fountain's first ordinary off-season in years. On its page for Rock Creek Park's fountains, the Park Service says it turns off its four DC fountains in winter to prevent damage and usually turns them back on in spring or summer, depending on temperatures and maintenance status. That puts the restart sometime in 2027, with the timing set by the weather.
For people who use the park every week, the lawns probably mattered more this year than the water. In March, The 51st reported that the original plan had the park closing from March 23 to September 4 for grass restoration and fountain repairs. It named picnics, yoga classes and the drum circle among the things affected. Greater Greater Washington reported that nearly 3,500 people signed a petition against a summer-long closure and that a group called @KeepMalcolmXOpen held rallies. The Park Service started turf work on the upper level around April 27. It kept the walkways open and fenced the two big grass panels while the new turf took root.
The fences came down and went back up more than once. Greater Greater Washington reported that the upper-lawn fencing came down on July 1 for a federal ceremony, was back up within a week, and came down again on August 17. In the fall the Park Service closed the two large upper-level grass panels again, from 6 a.m. on October 13 through 5 p.m. on November 9, for more restoration work. Its closure notice said other parts of the park would stay open during that time. That closure has ended, and the November 18 PoPville post shows the fencing down.
The Sunday drum circle has played in the park for more than 50 years, according to Greater Greater Washington. Its usual spot is the south end of the upper level. At a March 31 town hall reported by The 51st, Rock Creek Park Superintendent Brian Joyner said that section would not be closed during the lawn work.
The park's hours change with the season. From November through April it is open from 5 a.m. to 9 p.m., and from May through October it stays open until midnight. The earlier closing time now applies to evening walks after a holiday dinner.
The off-season is a good time to look at the park's other features. The armillary sphere on the lower plaza is a replica the Park Service installed on November 6 and 7, 2024. It was rebuilt from historic photographs and drawings after the original was removed in the late 1970s because of damage and vandalism. The Joan of Arc statue on the upper level is the only equestrian statue of a woman in Washington. It was restored that same November, and the work included replacing a missing piece of the spur and part of the bridle. The Dante Memorial, the James Buchanan Memorial and the Serenity statue are also in the park.
With the water off, the walls themselves are easier to see. According to the Park Service, Meridian Hill was a testing ground for concrete aggregate, a material made with pebbles chosen for size and color. Workers pulled the forms while the surface was still soft enough to treat, then used wire brushing and acid washing to bring out the texture. Construction started in 1914, and the park was not fully finished as a formal park until 1936. The name dates to 1819, when John Porter built a mansion on the grounds and called it Meridian Hill because it sat on the exact longitude of the District's original milestone marker. That marker was set in 1791 by Major Andrew Ellicott, with help from the astronomer and mathematician Benjamin Banneker.
The holiday calendar is a few blocks east of the park. District Bridges is running Mercadito, an outdoor food market at Tequila y Mezcal, 3475 14th St. NW, on Fridays, Saturdays and Sundays from November 20 through December 27, 9 a.m. to 5 p.m. Its listing names birria, tamales, pupusas and burritos, with local art vendors joining on some days. The Friday after Thanksgiving is one of the market days. On Friday, December 4, the Columbia Heights Tree Lighting and Holiday Market runs from 5 to 9 p.m. at Columbia Heights Civic Plaza, 1400 Park Road NW. The event listing mentions local shopping, hot cocoa and music.
If you want to compare winter with summer, the Park Service shuts down the other three Rock Creek Park fountains on the same schedule. They are the Newlands memorial fountain at Chevy Chase Circle, near our home base in Chevy Chase, the fountain at Georgetown Waterfront Park in Georgetown, and the Kahlil Gibran Memorial near the U.S. Naval Observatory.
If you own a home a short walk from the park and wonder how this year's changes affect its value, Vassar Broermann Group offers a free home valuation, and you can have that number before the water comes back in spring.
November 26, 2026
November 19, 2026
November 12, 2026
November 5, 2026
October 29, 2026
October 22, 2026
October 15, 2026
October 8, 2026
October 1, 2026
Get assistance in determining current property value, crafting a competitive offer, writing and negotiating a contract, and much more. Contact us today.