Eric Broermann September 22, 2017
Nearly three years after the design team was selected, nonprofit Building Bridges Across the River (BBAR) continues moving forward with plans for the 11th Street Bridge Park, which will repurpose the old 11th Street Bridge’s three concrete piers (map) into the city’s first elevated park.
On Monday night, BBAR, the District Department of Transportation (DDOT), and architecture team OMA+OLIN gave an update to the community of the project’s progress and a few design changes while presenting new images of the massive project.
For the past year, the development team has been engaged in the pre-construction phase, studying the engineering and environmental logistics of the site. Consequently, the design has been streamlined somewhat.
To ensure feasibility based on the load-bearing capacity of the existing piers, the bridge park has been slimmed down somewhat, shrinking from 139 feet wide to 116 feet wide at its widest point on the east side of the Anacostia River. A path from the east side to the west side has also been widened to accommodate emergency vehicles. While the programming on the park will remain the same, it has been resized accordingly.
The planned environmental education center has also been moved from its original placement at the shoreline to near the park entrance at Good Hope Road, moving it out of the floodplain. The concrete massing of the piers will also be broken up somewhat to create a lighter appearance.
The Park, which will be the length of three football fields, will be comprised of two see-sawing planes that create a triangulated park activated with such features as a play area, café, boat launch, community farm, hammock grove and an amphitheater. There will be several access points to the plaza atop the park from the adjacent pedestrian and bike path on the current 11th Street Bridge. Waterfalls on either end of the bridge and an array of native trees will help alleviate air pollution from the roadway.
While progress has been made on the equitable development portion of the project, BBAR is collaborating with the Urban Institute to issue a report on the project’s potential impact on housing in its surrounding neighborhoods by the end of the year. The development team will be meeting with the Commission of Fine Arts for a conceptual design review in October, followed by an approval meeting with the National Capital Planning Commission in November.
Below are new images of the park from OMA+OLIN.
Source: dc.urbanturf.com
October 3, 2024
New Eligibility & More Changes: Oct 2024
September 3, 2024
It's not just about the rate!
April 3, 2024
It’s important to figure out which shade will complement the furniture and textiles.
April 3, 2024
Let’s take a look at when paint works, what colors of paint to use on your cabinets.
March 14, 2024
Each State has slightly differing MCC eligibility guidelines and requirements, such as.
January 26, 2024
A question that almost every prospective client asks us is how we handle evictions.
November 1, 2023
This party was truly memorable and everyone had a great time catching up, and eating some food.
October 18, 2023
This was a great thing to know when helping our out-of-state client to sell their investment property.
August 16, 2022
We have always felt presentation is key to selling for top dollar – even in a strong seller's market.
Get assistance in determining current property value, crafting a competitive offer, writing and negotiating a contract, and much more. Contact us today.